23rd St. Columbus
Project Name: 23rd St. Columbus | Project Number: NH-30-5(134) | Control Number: 32234
About the Project
The Nebraska Department of Transportation (NDOT) will reconstruct approximately 2.69 miles of the existing pavement on 23rd Street starting just east of the north junction of U.S. Highway 81 (US-81) and 23rd Street, and extending just east of the East 11th Avenue intersection. The project will consist of removing and replacing pavement, four turn lanes (one right, three left) will be extended and five right turn lanes will be added. Curb inlets and storm sewer will be reconstructed and new pedestrian facilities will be constructed. In addition, driveways will be consolidated where possible and roadway lighting and traffic signals will also be updated with this project.
Project Updates
Sept. 23, 2024
Weather permitting, starting Sept. 24, the south leg of 18th Avenue, adjacent to U.S. Highway 30 (US-30/23rd St), will be closed to traffic. This closure is intended for pavement reconstruction and the construction of the storm sewer, according to the Nebraska Department of Transportation (NDOT).
Aug. 2, 2024
Weather permitting, starting Aug. 5, the north leg of the intersection of 30th Avenue and U.S. Highway 30 (US-30) will be closed to traffic. This closure will be in place for the construction of storm sewer inlets, water main relocation, and concrete pavement. The work at this intersection is anticipated to be complete towards the end of August.
On Aug. 9, the north leg of 26th Avenue and US-30 will be closed to traffic. In addition, the north leg of 23rd Avenue and US-30 will reopen to traffic. This traffic configuration will be in place for the construction of new concrete pavement. The work at the 26th Avenue intersection is anticipated to be complete in Sept.
May 15, 2024
Weather permitting, starting May 17, 2024, the north leg of the intersection of Pershing Road and U.S. Highway 30 (US-30) will temporarily reopen to traffic. Future closures at this intersection will occur for subgrade and paving operations.
In addition, the north leg of 23rd Avenue and US-30 will be closed to traffic starting May 20 for storm sewer construction. This segment is anticipated to be closed for one week.
Lastly, the north leg of the intersection of 18th Avenue and US-30 will remain closed for further underground utility work. The intersection is anticipated to be back open to traffic in July.
April 25, 2024
Weather permitting, starting April 26, 2024, the north leg of the intersection of Pershing Road and U.S. Highway 30 (US-30) will be closed for construction of underground utilities. This work is anticipated to be completed in mid-May.
In addition, the north leg of the intersection of 18th Avenue and US-30 will remain closed for further underground utility work. The intersection is anticipated to be back open to traffic in late May.
March 1, 2024
Weather permitting, starting March 4, lane restrictions will occur at E 6th Avenue for the U.S. Highway 30 (US-30) improvement project. Eastbound and westbound traffic will be reduced to two-lane, two-way traffic configuration in the newly constructed westbound lanes on US-30. Northbound and southbound traffic will be reduced to two-lane, two-way traffic configuration in the southbound lanes of E 6th Avenue. This work is anticipated to be completed in eight weeks.
In addition, on Wednesday, March 6, construction of segment two of the US-30 improvement project from just west of 26th Avenue to just east of 16th Avenue will begin. Traffic will operate in the existing eastbound lanes in a two-way, two-lane configuration while the westbound lanes are being constructed.
Construction of segment two of the US-30 improvement project, from 25th Avenue to 16th Avenue, is expected to be complete in fall 2024.
February 9, 2024
Weather permitting, starting Feb. 12, traffic signal work will occur at multiple intersections to prepare for the next phase of construction on the U.S. Highway 30 (US-30) improvement project, according to NDOT.
Beginning Monday, Feb. 12, temporary lane restrictions will occur at the signalized intersections on US-30 from 26th Avenue to 18th Avenue to install temporary traffic signals to operate during construction. This work will occur during daytime hours only and is anticipated to be completed by Friday, Mar. 1. Traffic will be controlled by the existing traffic signals during this time.
Additional traffic signal work includes the intersection of 3rd Avenue and US-30 on Tuesday, Feb. 13 and the intersection of 14th Avenue and US-30 on Thursday, Feb. 15. On each of these respective days, traffic will be reduced to one lane in each direction for one day to wire and connect new traffic signals and remove the temporary signals. Traffic on each day at the respective intersections will be controlled with a four-way stop configuration during this time.
The second construction segment of the US-30 improvement project, from 25th Avenue to 16th Avenue, is expected to begin in Mar. 2024.
November 15, 2023
Access to U.S.-30 from the south on 3rd Ave will be closed to traffic on Nov. 16th from 8 AM until 3 PM. This temporary closure is for the construction and installation of signal poles.
October 16, 2023
Weather permitting, beginning Oct. 20, 2023, access to US-30
from the south on 3rd Avenue will be closed for approximately two weeks, according to the Nebraska Department of Transportation (NDOT). This closure is required for new paving of the reconstructed highway in the area. Access to local businesses will be maintained. Information regarding the US-30 improvement project can be found on the project website, ndot.info/32234. NDOT also encourages the public to follow the latest project updates on
Twitter/X @23rdStColumbus and @NEColumbus.
October 6, 2023
Work continues on construction of new storm sewer pipe and inlets from 3rd Ave to East 6th Ave. Upcoming construction activities include construction of foundation course from 10th Ave to 3rd Ave and mainline paving east of 16th Ave. Motorists are reminded to drive cautiously in and near work zones.
August 18, 2023
Weather permitting, starting on August 23 at 8 p.m., traffic along US Highway 30 (US-30/23rd Street), from east of 16th Avenue to the east side of E 11th Avenue, will be switched to the westbound lanes for construction activities. Traffic will be reduced to two-lane, two-way traffic in some locations and will be controlled by barricades and other traffic control devices.
Construction activities including utility work, storm sewer upgrades and concrete paving have been completed in the westbound lanes. The traffic shift to the newly constructed westbound lanes is necessary to allow for similar construction activities to occur in the eastbound lanes. Construction in the median through this area is expected to take place later this fall.
July 5, 2023
Work continues on the sanitary and storm sewers as the contractor began paving activities on the westbound lanes beginning at East 12th Avenue continuing westbound. The contractor has also begun the removal of the building located at the northeast corner of 18th Ave/23rd St where a future right-turn lane is planned. Motorists are reminded to drive cautiously in and near work zones.
March 21, 2023
Weather permitting, construction work will begin on March 28 on the U.S. Highway 30 (US-30) improvement project, according to the Nebraska Department of Transportation (NDOT).
The westbound lanes from 16th Avenue to E. 12th Avenue will close at 8 p.m. While the westbound lanes are closed, traffic will operate in two-lane, two-way configuration in the existing eastbound lanes.
During construction, temporary turn signals and other temporary traffic control devices and traffic patterns will be in effect, including lane shifts. Access to all properties will remain open during construction, however intermittent driveway and intersection closures are expected.
Information regarding the US-30 improvement project can be found on the project website, ndot.info/32234. The NDOT also encourages the public to follow the latest project updates on twitter @23rdStColumbus and @NEColumbus.
January 26, 2023
The Nebraska Department of Transportation (NDOT) will hold a pre-construction public information open house meeting regarding improvements to U.S. Highway 30 (US-30) from just east of the north junction of U.S. Highway 81 (US-81) and US-30, extending to just east of the East 11th Avenue intersection in Platte County. The meeting will be held at the American Legion Hartman Post 84, 2263 3rd Avenue, in Columbus on Thursday, February 9, 2023, from 5:00 to 7:00 PM.
Initial construction is scheduled to start in spring 2023. The highway project would be constructed under traffic with lane closures controlled by approved temporary traffic control strategies and devices. Access to adjacent properties would be maintained during construction but may be limited at times due to phasing requirements. Additional details will be available online and at the open house.
There will be a formal presentation at 5:15 PM, and personnel from the Department of Transportation and the contractor will be available to answer questions. Information regarding the proposed project will be made available on the NDOT website at ndot.info/32234.
November 16, 2022
Construction began November 14 on the east crossover in preparation for the next phase of the reconstruction project on 23rd Street in Columbus. Drivers should expect lane closures to both westbound and eastbound traffic between East 6th and East 11th Avenue to just east of East 14th Avenue on 23rd Street. Work includes drainage work, grading, and placement of concrete to construct a crossover. Anticipated completion is November 30, 2022. Project information available on the NDOT website at: ndot.info/32234
February 9, 2023 Pre-Construction Public Information Open House Meeting
- Fact Sheet - English | Spanish
- Meeting Presentation
- Meeting Boards
- Mosaic
- Recorded Presentation
August 11, 2022 Pre-Construction EPA Mitigation Public Information Open House Meeting
- Fact Sheet - English | Spanish
- Meeting Presentation
- Meeting Boards
- Postcard - English | Spanish
- Legal Notice - English | Spanish
- Roll Plot
February 12, 2019 Public Meeting
Items from February 22, 2018 Public Meeting
- Meeting Notice – English | Spanish
- Meeting Handout - English | Spanish
- Meeting Display Boards
- Aerial Mosaic
Items from Stakeholder Meetings on April 17-19, 2017
- Stakeholder Meeting Handout
- Project Location
- Comment Sheet - Your input is important to us. NDOT and the City of Columbus would like your input regarding the potential improvements to 23rd Street (US-30). Please provide us with information outlined in this comment sheet via email, mail or the form located below.