N-370 – Omaha
Project Name: N-370 - Omaha | Project Number: NH-STP-HSIP-50-2(135) | Control Number: 22602
Project Updates
June 14, 2024
Construction progress as of June 14, 2024.
May 28, 2024
Beginning today, May 28, weather permitting, Millard Avenue will be closed from U Street to 144th Street through Aug. 2024 for pavement replacement. Local traffic will be maintained. Detours include:
- Southbound on Millard Avenue: Westbound on Q Street to 144th Street
- Northbound on 144th St: Q Street then eastbound to Millard Avenue
Construction on the N-370 – Omaha project began in spring 2024 and is expected to be complete in summer 2025. The project includes concrete and bridge repairs as well as guardrail replacement along N-50. This work addresses deteriorating road conditions and optimizes traffic flow at intersections, ultimately contributing to safer and more reliable transportation infrastructure.
April 30, 2024
Beginning Monday, April 29, 2024, weather permitting, work is continuing on the Nebraska Highway 50 (N-50) from N-370 to Interstate 80 (I-80). One lane in each direction will be closed through summer 2024 for bridge and concrete pavement repairs. Construction on the N-370 – Omaha project began in spring 2024 and is expected to be complete in summer 2025. The project includes concrete and bridge repairs as well as guardrail replacement along N-50. This work addresses deteriorating road conditions and optimizes traffic flow at intersections, ultimately contributing to safer and more reliable transportation infrastructure. For more information on the project, please visit ndot.info/22602.
Information
April 2024 Pre-Construction Public Information Meeting
- Meeting Notice
-
Narrated Presentation
March 2022 Public Information Meeting
- Meeting Handout
- Meeting Displays
- Project Overview
- N-50 & Harrison Street Intersection
- Narrated Presentation
- Meeting Notice
- Meeting Invite