PROJECT

 

50th St. - I-480, Omaha, CN 22855, NH-MTIS-80-9(203)

   
Delivery Method:  Design-Build
Advertisement Date:  January 30, 2026

 

Anticipated Procurement Schedule:
  • SOQ Due Date - February 27, 2026
  • Final RFP - May 20, 2026
  • Proposal Due Date - September 18, 2026
  • Best Value Selection - October 16, 2026
  • Construction - Spring 2027

 

Key Repairs:

  • Reconstruction of the existing pavement within the project limits.
  • Widening of one additional lane in the westbound direction to improvement operations through the 42nd Street interchange.
  • Improvements such as  lighting upgrades, curb & flume, culvert work, bridge repairs, bridge deck replacement, bridge approach replacement, bridge widening, and guardrail replacement.
  • The 42nd Street Interchange ramps may be realigned to connect to the widened I-80 Mainline pavement.
  • The bridges over 42nd Street (Structure Numbers S080 45180L and S080 45180R) will be rehabilitated and widened for both directions.
    • The westbound direction will match the additional lane within this project.
    • The eastbound direction will accommodate the future 6th lane with the on-loop across the bridge before merging into I-80.
  • The bridge carrying 36th Street (Structure Number S080 45231) will be repaired.
  • The bridges over 50th Street (Structure Numbers S080 45103L and S080 45103R) will be rehabilitated.
  • The bridge carrying 36th Street (Structure Number S080 45231) will be repaired.
  • The bridge over Union Pacific Railroad (Structure Number S080 45252) will be repaired.
  • The bridge carrying 32nd Avenue (Structure Number S080 45266) will be repaired.
  • This project will be constructed under traffic with lane closures controlled by appropriate traffic control devices and practices.
  • Construction activities may be required to be accomplished at night.
  • No Additional property rights are anticipated to be required to build this project

 

The project is approximately 1.8 miles in length and is located on I-80 in Douglas County, starting approximately just west of the bridges carrying I-80 over 50th Street and extending east to approximately just west of the bridges carrying I-80 over the I-480 on ramp. Construction may begin and/or end approximately 500 feet ahead of or beyond the actual project limits to accommodate transitioning the pavement.

 

The existing roadway on this segment of I-80 generally consists of 12-foot-wide composite lanes that vary in number from seven to three, in both eastbound and westbound directions, and 12-foot-wide outside shoulders, of which 12 feet is paved in the westbound direction and 10 feet is paved in the eastbound direction, with composite surfacing, and 12.5’-foot-wide composite inside shoulders.

 

 

 

 

 